摘要:建筑结构在随着我国经济的快速发展,建筑行业也取得了飞速的进步并有了很大的成就。在设计使用年限内,结构应具有设计规定的可靠度。在达到设计规定的设计使用年限后,结构或结构构件的可靠度可能会降低,但从技术上讲,并不意味着其已完全失去继续使用的安全保障。文章主要对于小区结构设计常见的设计方案进行了分析,并且给出了一些实质性的建议。
关键词:工程概括 设计与解决方案 人防工程
Abstract: the building structure in along with the rapid economic development of our country, the construction industry also made a rapid progress and has made a lot of achievements. In the design in the use fixed number of year, structure design codes should have the reliability. In the design of the provisions to design use fixed number of year, structure or structures of the component reliability may decrease, but technically, does not mean that it has completely lost to continue to use the security. This article mainly for community structure design of the common design schemes are analyzed, and gives some advice of substance.
Keywords: engineering summarized design and solutions of civil air defense projects
中圖分类号:TB482.2文献标识码:A 文章编号:
1、工程概况
1.1自然状况
小区位于安阳市某合围地段,小区内共有21幢单体建筑,除几栋多层建筑外,其余均为16层左右的高层建筑。在各单体之间的地下部分设地下车库,车库与各单体的地下室相连。在平面上整个小区分为三块,各块间是5m左右宽的土带。
1.2地质状况
本区地处安阳市某地漫滩地段,地形较为平坦,地面海拔在120m左右。该建筑场地地层为第四纪冲—淤积地层,上部为粘土层,砂类土中含有薄厚不均的粘土夹层。勘探期间其初见水位:4·50~5·50m,静止水位为3·90~4·20m,水位较高。地震基本烈度为8度,抗震等级为二级,Ⅱ类场地土。此区地基土为季节性冻土,其标准冻深为1.0m。
1.3建设周期
整个小区分两期建设,一期工程于2005年7月开工,二期工程于2006年2月开工。一期工程主体于2006年5月完成,到2007年8月二期工程主体多数已完成。
2、设计难点与解决方案
2.1地下水的处理
由于建筑场地地下水位较高,而且一期工……