On the municipal drainage project quality control and common problem prevention
Wang Bei
(Raoyang County Water Authority Raoyang Hebei 053900)
【Abstract】The municipal water supply and drainage is one of the important facilities, municipal facilities to be normal use, the pros and cons of the quality of the project not only affect urban functions into full play, and roads in good condition, urban environmental protection and urban flood control and drainage, have a direct impact. This article preparation, combined with years of field experience from the construction site management, common quality defects and measures three aspects of the control points and measures of quality of municipal water supply and drainage construction.
【Key words】Quality management;Quality common problem;Treatment measures
1. 施工准备阶段
1.1 熟悉图纸:施工人员只有熟悉了图纸,结合图纸掌握了排水管线的长度、坡度、走向、管材直径、井位数以及与施工区域有关的地形、地貌、地物等情况,才能在施工过程中有条不紊地应对一切突发事件。
1.2 测量放线:施工前要认真按照施工测量规范和规程进行交换桩复测与保护,不得擅自变更,防止出现产生积水甚至倒坡现象,遇到建筑物须避让时,需出具设计变更。
2. 施工现场管理
2.1 沟槽开挖、支护、垫层。
2.1.1 在开挖前摸清地下原有管道、电缆和其他构筑物的位置,将调查结果和处理方案送交业主和相关管理单位确认,以便采取相应的保护、迁移或设计变更等措施,保证开挖顺利进行。
2.1.2 在沟槽开挖过程中,及时做好管道基础施工准备,不使沟底土基暴露时间过长,造成不必要的损失。
2.1.3 混凝土基础第一次浇筑成水平形状,待安管后再浇管座。混凝土用插入式振动器振实后,再用平板式振动器振平及抹平,基础浇筑完毕后2h内不得浸水,并及时进行养护。
2.2 管道安装。
2.2.1 管材的选用和检查:管材要有质量部门提供的合格证和力学试验报告等资料,管材表面平整,无松散露骨和蜂窝麻面形象,并在安装前再次逐节检查,对己发现或有质量疑问的管材应立即停止使用或进行有效处理后方可使用。……