Application of T-beam Precast Construction Technology in Large Longitudinal Slope Site
阳长江,李丽萍
(重庆建工市政交通工程有限责任公司,重庆 400021)
大纵坡场地T型梁预制施工技术的应用
Application of T-beam Precast Construction Technology in Large Longitudinal Slope Site
阳长江,李丽萍
(重庆建工市政交通工程有限责任公司,重庆400021)
摘要:该文介绍了大纵坡情况下的T梁预制施工技术通过合理确定纵坡坡度、龙门吊及其基础的斜坡优化和钢筋定位骨架的使用,实现了大纵坡梁场T梁的预制施工,解决了在纵坡地段梁场建设“规划难、成本高”等现实问题。该技术具有成本低、速度快、安全性高等一系列优点,具有一定的推广价值和现实意义。
关键词:大纵坡;龙门吊优化;T型梁预制;钢筋定位骨架
Abstract:The T-beam precast construction at a large longitudinal slope is completed and the construction problems of“thorny planning and high cost“are solved through the reasonable determination of longitudinal slope, the optimization of gantry cranes and its foundation slope as well as the adoption of steel location skeleton. This technology is proved to own the advantages of low cost, high speed and impressive safety, so it has significant value for promotion and practice.
Keywords:large longitudinal slope;gantry cranes optimization;T-beam precast;steel location skeleton
在山岭地区修建高速公路,不可避免地要进行预制场的选址、场内规划等工作。由于山岭地区高差大,加之陡峻的山坡和曲折幽深的河谷,形成了错综复杂的地形,这时常使得预制梁场场内规划建设受路段纵坡大的客观条件所限[1]。然而,采用相邻标段合并预制或者委托相邻标段进行预制,又存在成本高、管理难度大、工期影响因素多等问题[2]。因此,还需妥善解决在大纵坡地段下进行桥梁预制的问题。
重庆南川至贵州道真高速公路TJ2工区段中的桥梁建设共需完成555片T梁预制工作。由于受地形限制,梁场建设只能选择在路基上进行,但其上存在较大纵坡,坡度为3.8%,如何妥善解决梁场场内规划、制梁质量与运梁安全等问题是一项相当重大的技术难题。
该技术于2015年10月10日通过重庆市城乡建委组织的关键技术鉴定,被专家一致认为该技术达到国内领先水平。……