杨英鸽 王瑞 袁吉娜 袁宾 李中生

摘要】南水北调中线一期工程是我国目前最大一项输水工程,途经河南、河北、北京、天津四个省市,输水总干渠长1432Km,由于供水线路长遇到的地质情况复杂多变,因此在地基处理上也各不相同,就新乡段而言,分别有湿陷性黄土的强、重夯地基处理,水泥粉煤灰碎石桩(CFG桩)地基处理,水泥土换填等。本文从三种地基处理的工序、施工过程、质量控制要点入手,阐明了具体的施工方法。
【关键词】强重夯;湿陷性黄土;CFG桩;水泥土换填
On the Construction of foundation treatment NORTH
Yang Ying-ge1,Wang Rui1,Yuan Ji-na2,Yuan Bin1,Li Zhong-sheng1
(1.Henan Provincial People's Victory Canal AuthorityXinxiangHenan453003;
2.Henan Branch source of water conservancy construction detection LtdZhengzhouHenan450003)
【Abstract】North Water Transfer Project is one of the largest one water project, through Henan, Hebei, Beijing, Tianjin, four provinces, water main canal of length 1432Km, due to the geological conditions encountered in complex water supply line lengths, so foundation treatment also varies, the Xinxiang section, respectively, of strong loess of heavy tamping foundation treatment, cement and fly ash gravel pile (CFG pILE), cement soil of replacement and the like. In this paper, three kinds of ground handling processes, the construction process, quality control points to start to clarify the specific construction methods.
【Key words】Strong heavy ram;Ioess;CFG pile;Soil cement Replacement
1. 湿陷性黄土夯实地基处理 此方法是反复将夯锤提到一定高度使其自由落下,给地基以冲击和振动能量,使地基土密实。施工前,应对所处理地基进行复堪,掌握相关的地质指标,如处理层深度、地下水位和地层含水量等数据。
强、重夯施工工序为:测量放样→ 取原状土检测 →第一遍夯击→第二遍夯击→第三遍夯击→试验检测
1.1工序检验程序。如图1所示,施工过程中应对施工方法、施工工艺进行经常性的监督检查,发现违规行为要及时整改。对可能影响质量的问题及时指令施工单位采取补救措施,对不符合设计指标要求的必须进行返工处理。
图1工序质量控制工作程序框图 1.2强、重夯处理湿陷性黄土的技术标准。
(1)满足处理深度范围内土层的湿陷系数应小于0.015的规范要求。根据设计标准强夯参数为:单击夯击能2000KN.m,锤重20t,底面直径2.5m,落距10m。夯击数及遍数为10击4遍,第一遍按正三角形布置,中距6.5m,第二遍夯点在第一遍之间布置,第三遍满堂布置,最后一遍夯锤落距可降至4~6m。……