On the Three Gorges Project Construction Quality Management and concrete plant improvement
Xu Ting-ting
(China Water Conservancy and Hydropower No, 3 Engineering Bureau LtdXianShaanxi710016)
【Abstract】High quality requirements of the Three Gorges Project, the Three Gorges Corporation specifically formulated the "Three Gorges standard", the purpose is to better ensure the quality of construction of the Three Gorges Project. Left two engineering construction, construction quality, although made some achievements, but still need to improve and improve. Right bank of the three construction process, through the development of specialized concreting measures to enhance the quality of management and operational coordination and communication between the layers and other measures to make the right bank of three construction quality than the left bank of the two construction quality on a higher level. I, as a builder of the Three Gorges Project, the Three Gorges Project to talk about the following major concrete construction quality management and quality improvement.
【Key words】Three Gorges;Concrete;Quality;Management;Improved
1. 工程简介
三峡水利枢纽工程主要包括:大坝、水电站厂房、通航建筑物。电站厂房为坝后式厂房,由上游副厂房、主厂房、下游副厂房及尾水渠等建筑物组成。分别在左岸电站厂房安装14台、右岸电站厂房安装12台700MW的水轮发电机组。
2. 左岸二期混凝土施工质量管理
2.1文件资料控制。
(1)混凝土施工中,避免错检、漏检是质量管理基本要求,要达到这个目标,首先要管理好作为施工和验收依据的各类图纸、技术措施和各种相关通知单。为此,质量管理部门内部在前后方建立了严格的收发和领文制度,前方人员对收到的通知单必须及时更改到相关的图纸或有关文件中,同时注明更改依据并签名。对发到前方的所有文件和通知单,前方值班人员实行阅后签名制。部门主任不定期对前方的文件资料管理进行检查和督促。通过这种制度有效地防止了设计修改的遗漏,也使每位质检员能及时熟悉各种技术措施和相关要求,从而有效地避免了错检和漏检。……