徐凯
【摘要】本文作者结合某水库溢洪道施工实例,从溢洪道土石方开挖、溢洪道混凝土施工技术等环节来详细地探讨溢洪道施工的实施,总结出该项目所采取的成功施工经验,为同行提供参考借鉴。
【关键词】水库工程;溢洪道;施工加护
Analysis on Construction Technology of Reservoir Spillway
Xu Kai
(Araigou Reservoir Construction Management BureauTurpanXinjiang838000)
【Abstract】In this paper, the construction practice of a spillway in spillway is discussed in detail from the excavation of the spillway and the concrete construction technology of the spillway. The experience of the successful construction of the spillway is summarized, which can provide reference for the peers.
【Key words】Reservoir engineering;Spillway;Construction and protection
1. 工程概况
本工程溢洪道由进水渠、控制段、泄槽和消能段组成。该水库水渠系开挖而成,控制段上游30m为平直段,矩形断面,宽40m,底板高程167m,采用C20混凝土衬护。导墙为直立式混凝土结构。控制段水平投影长30m,设3孔闸门,每孔净宽12m。溢流堰为WES实用堰,堰顶高程171m,设弧形钢闸门控制泄洪,闸门由固定卷扬式弧门启闭机启闭。启闭机室地坪高程194m。启闭机室上游布置宽6m的交通桥。泄槽纵坡为1∶3,净宽40m。底板为C30混凝土,厚0.5m,下设多孔排水管系统;边墙为C25混凝土结构。出口采用挑流消能,反弧半径25m,挑流鼻坎高程144.64m,挑射角25°,最大挑距79.03m。挑流鼻坎采用C30混凝土结构。为防止小流量时水流冲刷,在挑流鼻坎后设0.8m厚C15混凝土护坦保护。冲刷坑需预挖。控制段固结灌浆,孔深3m,孔距、排距均为3m,梅花形布置。溢流堰的开挖面不进行帷幕灌浆。进水渠开挖边坡迎水面进行喷混凝土保护处理。
2. 溢洪道土石方开挖
2.1基础开挖及处理、边坡支护方案分析。
对溢洪道基础开挖,应当使开挖符合施工详图或设计规定的边界,并使开挖面以下或以外的基岩保持设计要求的完好状态。对永久边坡或倾斜、垂直或水平的建基面,按设计开挖线布置预裂孔,进行预裂爆破及控制爆破。……