济南黄河特大桥主桥水中基础施工技术

2017-05-11 10:19:31孙宇
价值工程 2017年15期
关键词:施工技术

孙宇

摘要: 介绍了济南黄河特大桥主桥水中基础施工采用的水上栈桥、水中平台、气举反循环钻机钻孔、钢板桩围堰、大体积混凝土施工等关键技术。施工方案选择合理,针对性强,简便实用,易于操作,结构受力明确,降低了施工成本,很好的解决了该桥水中基础施工难题,对同类工程有很好的借鉴作用,可以推广应用。

Abstract: This paper introduces the key technologies of water bridge, water platform, air lift reverse drilling rig drilling, steel sheet pile cofferdam and mass concrete construction in the construction of water main foundation of Jinan Yellow River Long Span Bridge. The construction scheme is reasonable, targeted, simple and practical and easy to operate, and it has clear force structure, reduces the construction cost, and provides a good solution to the bridge water foundation construction and gives similar projects a good reference, so its application can be promoted.

关键词: 特大桥;水中基础;施工技术

Key words: long span bridge;foundation in water;construction technology

中图分类号:U445.4 文献标识码:A 文章編号:1006-4311(2017)15-0123-03

1 工程概况

京沪高速铁路济南黄河特大桥起讫里程DK406+918.874~DK412+062.274,总长5143.4m。主桥采用(112+3×168+112)m下承式等高度连续性梁柔性拱钢桁梁桥,主桥墩为0-5号,0#承台位于北岸淤背区,1#、2#承台位于主河槽(常年有水),其它承台主要分布在南岸滩地。1号墩与2号墩均采用28根?准2.5钻孔灌注桩,钻孔桩长分别为90m、102m;承台厚度6.0m,平面尺寸为42.5×23.3m。

桥梁位于山东省济南市槐荫区,地层结构主要是第四系河相粉质土结构,其间多夹粉、细、中沙及粉土、薄层粘土或透镜体,其中覆盖层40m以下分布着姜石层。桥梁设计水位34.960m,最高通航水位34.460m,河流每秒平均流速为2.07m,在枯水期,黄河只有主河槽有水,设计施工洪水位30.500m,现场探测墩位水深约5m。其中1、2号承台位于黄河主河槽,承台底面标高21.0m,一般水位为25.0~30.5m。

2 方案确定

2.1 施工通道方案

由于黄河水流流速较高,冬季还存在流冰现象,加之黄河调水调沙40天左右以及夏季洪水期等影响因素,建造浮桥式施工通道既不安全,又要考虑诸多不确定性的因素。经过讨论之后决定施作以贝雷梁钢栈桥为主的施工栈桥作为施工通道。……

登录APP查看全文

猜你喜欢
施工技术
建筑混凝土施工技术要点及有效对策分析
桥梁预应力工程的施工技术研究
高压输配电线路工程施工技术控制之我见
试析建筑工程施工技术及其现场施工管理探讨
浅析水利工程建设中的混凝土施工技术与施工管理
探讨水利水电工程防渗墙的施工技术
高层建筑主体结构施工技术及质量控制研究
施工技术在水利水电工程中的重要应用探究
水利水电工程建筑的施工技术及管理分析
试论关于水利工程冬季施工技术