瞿洪海++范广存



【摘要】本文叙述了在预制箱梁安装过程中,由于桥头引道不具备上梁条件,可能导致工期延误。因而采取了门式提梁机侧方上梁的方式,与采用大型汽车吊相比,既安全可靠又节省费用,同时保证了工程进度,可谓一举多得。
【关键词】编制依据;工程概况;施工方法及技术措施
Talking about the Application of Door - type Beam Machine
Qu Hong-hai,Fan Guang-cun
(Jiangsu Zhongyuan Engineering Management Co., LtdNanjingJiangsu211500)
【Abstract】This paper describes the installation of prefabricated box girder in the process, because the bridge approach Road does not have the upper beam conditions, may lead to delays in the duration. And thus take the door beam beam side of the beam on the way, compared with the use of large car crane, both safe and reliable and cost savings, while ensuring the progress of the project can be described as multiple purposes.
【Key words】Preparation basis;Engineering overview;Construction methods and technical measures
1. 前言
目前,我国各大城市的基础设施工程正在处于发展时期,城市高架桥、快速路作为解决城市交通拥堵的有效手段,正在被越来越多的应用。桥梁上部结构预制安装的形式由于受外界的干扰较小、施工精度高、质量有保证,箱梁预制和下部结构可以同时进行施工、实现流水化作业、从而节约工期,同时工程造价也比现浇箱梁更低。因此,呈现出强劲的发展势头。
2. 编制依据
(1)建质[2009]87号文《危险性较大的分部分项工程安全管理办法》;
(2)《架桥机安全规程》GB 26469-2011;
(3)《架桥机通用技术条件》GBT 26470-2011;
(4)《市政架桥机安全使用技术规程》JGJ 266-2011;
(5)《建筑施工起重吊装安全技术规范》JGJ 276-2012;
(6)《建筑施工安全检查标准》JGJ59-2011;
(7)《公路桥涵施工技术规范》(JTG/T F50-2011);
(8)《路桥施工计算手册》;
(9)《起重吊装常用数据手册》;
(10)《施工图设计》;
(11)《岩土工程勘察报告》;
(12)现场水文、地质、气象、交通、拆迁等施工作业环境条件的調查。
3. 工程概况
3.1工程简介。
某城市快速路改造工程为该市南北向城市主干道,沿线由北向南依次与东西向各城市主干道和高速公路相互连接,路线全长15.153Km。其中上跨高速公路的桥梁,采用预应力小箱梁预制安装的形式。本次预制梁架设共计160片,其中30m长的预制箱梁104片,35m长的预制箱梁56片。……