

【摘要】沙特SWCC长输管道项目大口径76寸管线,沿途地形高差悬殊,地貌复杂且地质条件为山区土石段,为克服山区陡坡地段施工困难,采取精准放线及模拟布管、修筑Z字形施工作业带、安全吊装、自制内对口器进行管道全自动组焊等关键技术措施。
【关键词】长输管道;山区陡坡;施工技术
Steep Slope Construction of Large Diameter Cement
Jiang Wei-hua
(Oilfield Construction Department, Jiangsu Petroleum Exploration BureauJiangduJiangsu225261)
【Abstract】Saudi SWCC long-distance pipeline project large-diameter 76-inch pipeline, along the terrain height difference between the complex, geomorphological complex and geological conditions for the mountain soil and rock section, in order to overcome the steep slope construction difficult mountain area, take the precise line and the simulation of the pipe, the construction of Z-shaped construction With the safety of lifting, self-made within the mouth of the pipeline for automatic welding and other key technical measures.
【Key words】Long pipeline;Mountain steep slope;Construction technology
1. 工程概况
沙特SWCC是世界上最大的海水淡化公司。输送介质为淡化海水。其中主线1930.4mm184公里,材质等级B~X65,壁厚15.88~22.22mm,管线采用3PE外防腐水泥砂浆内衬,成品管单根重量18~23吨,主线途径多为山区段,山地高低起伏大,设计最大坡度34°。
2. 施工流程
由于SWCC项目管道内防腐是水泥砂浆内衬,要求管线沟下焊接作业。陡坡施工顺序首先施工较缓的坡,再施工较陡的坡,已施工完较缓的坡作为另一边较陡坡的锚固(见图1)。
3. 主要施工难点技术措施
3.1修筑Z字形施工作业带。
(1)因为现场部分石方段为坚硬石方段,设备进场之后提前就要对陡坡段进行削坡处理。
(2)削坡使纵向坡度控制在16°以内(履带吊车最大爬坡能力16°)。破碎的土石方,每隔100m修筑一个临时的土石方堆放平台,以减少回填土石方运输的工作量。
(3)施工作业带宽度,Z字下方移动电站要离管沟边有1米安全距离。
(4)作业带夯实平整,防止横坡倾覆,保证机械安全通行要求。
3.2精准放线及模拟布管。
(1)由于山区起伏不平,施工有很多斜切弯头,在陡坡段需要对管线的实际长度跟水平长度的转换,这样便于测量放线,测量仪器使用RTK,管线图纸是按照长度:高程=1:10来的如图2:……p>