Analysis of cantilever pouring construction method
Wang Zhao-peng,Liu Fu-cun
(Mengyin Jian'an Construction Co., LtdMengyinShandong276200)
【Abstract】Since the emergence of the cantilever construction method in the 1960s, the prestressed concrete bridge has been continuously developed to large span. As the key equipment of its construction, the construction of hanging and hanging basket has also been developed continuously. It has laid a foundation for shortening the working period and increasing the economic benefit. It has achieved good construction effect and has been getting more and more in the modern bridge construction. application.
【Key words】Cantilever;Pouring
工程概况:汶河河大桥位于临沂市市城北区,横跨汶河,该桥主桥采用35+60+35米的三跨变截面预应力混凝土连续梁桥,横截面为单箱单室。根据受力情况采用三向预应力。主桥采用菱形挂篮施工,以21号墩、22号墩为两个t构,单t划分8个块段,施工时最大悬臂长度27.5m,悬臂浇筑最大长度4m,最大重量95吨,单t浇筑最大不平衡力控制在200kn以内。
1. 悬臂浇筑施工工艺
(1)悬臂法浇筑法又称无支架平衡伸臂法或挂(吊)篮法,所用的主要的设备是挂篮。通过挂篮的前移,对称地向两侧跨中逐段浇筑混凝土,并施加预应力,如此循环作业。
(2)其施工工艺流程:挂篮前移就位→调平模板→(钢筋制作)安装底板及腹板钢筋→安装内模→绑扎顶板钢筋→安装预应力管道→监理工程师验收→浇筑混凝土(制作试块)→混凝土养护、拆膜及接缝处理→预应力筋下料、穿束→张拉预应力筋→封锚、压浆→挂篮前移就位。
2. 菱形挂篮的组成和特点
挂篮主要由三个系统组成:主桁承重系统、底篮和模板系统、走行系统。菱形挂篮特点:结构简单,受力明确,整体刚度大,安全可靠,操作方便;前端及中部工作面开阔,便于挂篮轨道、腹板、底板钢筋、竖向预应力钢筋的安装,加快施工速度;……