殷凯
摘 要:文章分析了城市轨道交通地铁盾构隧道软土区域沉降的特点及原因,并结合武汉地铁的经验,提出了盾构隧道底部软土的判别原则;并综合考虑软土分布及周边环境等因素,提出了地面加固、洞内加固及地面加固与洞内加固相结合的三种软土处理措施,分析了其各自的优缺点及适用性;文章所提的盾构隧道软土判别原则及地层加固方式可为类似工程提供借鉴。
关键词:地铁;盾构隧道;软土;地层加固
中图分类号:U456 文献标志码:A 文章编号:2095-2945(2018)33-0120-03
Abstract: This paper analyzes the characteristics and causes of soft soil regional settlement of shield tunnel in urban rail transit, and puts forward the discriminating principle of soft soil at the bottom of shield tunnel based on the experience of Wuhan Metro, and comprehensively considers the distribution of soft soil and the surrounding environment. Three soft soil treatment measures, ground reinforcement, hole reinforcement and combination of ground reinforcement and tunnel reinforcement, are put forward, and their respective advantages, disadvantages and applicability are analyzed. The principle of soft soil identification and the method of stratum reinforcement of shield tunnel mentioned in this paper can be used for reference for similar projects.
Keywords: subway; shield tunnel; soft soil; stratum reinforcement
1 概述
城市軌道交通地铁盾构隧道在软土区域的沉降问题越来越受到关注。根据上海、杭州、武汉等地的监测,处于软土地层的盾构隧道在运营期沉降是一个长期的过程,其沉降往往需3~5年甚至更长时间才能达到稳定状态。
地铁盾构隧道运营期的沉降危害主要体现在以下四个方面:(1)长期沉降尤其是不均匀沉降过大,会影响盾构管片的结构安全性,造成管片开裂、掉块等现象。(2)盾构隧道沉降过大,会造成管片环缝或纵缝张开过大,进而造成管片漏水,将影响隧道正常使用,甚至造成结构耐久性不足的问题。(3)盾构隧道沉降过大,可能会造成隧道限界不足,并造成内部管线、接触网等设施的安全问题,影响列车的安全运营。(4)一旦运营期盾构隧道产生较大沉降,所能采取的有效补强措施较为有限,其实施效果也较难保证;同时由于列车已经处于正常运营状态,只能在夜晚列车停运的天窗时间进行补强施工,施工成本高昂,且对既有隧道运营会造成风险。……