基槽用固化土回填施工技术

2018-04-04 05:55:14张超王立根
价值工程 2018年10期
关键词:施工技术

张超 王立根

摘要: 在各类工程肥槽回填施工过程中,往往会遇到肥槽回填空间狭窄、回填深度较大、回填土夯实质量不稳定等难题。传统工艺多采用素土或者灰土分层使用小型夯实设备进行施工,施工难度较大、回填工期较长、回填的质量还难以控制,综合本项目“工期紧、任务重”等要求,本项目肥槽回填采用固化土。

Abstract: In the process of backfill construction of various engineering foundation trench, the problems of narrow foundation trench backfill space, large backfill depth and instability of backfill soil are often encountered. The traditional technology usually uses the plain soil or the lime soil stratification with small ramming equipment to carry on the construction, the construction is difficult, the backfill period is long, the backfill quality is still difficult to control, based on the requirements of "tight construction period and heavy tasks" of this project, solidified soil is used for backfill of foundation trench in this project.

關键词: 基槽;固化土回填;施工技术

Key words: foundation trench;backfill of solidified soil;construction technology

中图分类号:TU990.3 文献标识码:A 文章编号:1006-4311(2018)10-0136-04

1 工程概况

本标段管廊干线在政通东路正下方,运河东大街至玉带河大街处原混凝土沥青路面需翻修,政通东路(政通北街-通胡路),本标段综合管廊标准仓基槽宽度为18m,深度为8-14,主体结构宽度为15.35m,肥槽回填宽度为1m。

在各类工程肥槽回填施工过程中,往往会遇到肥槽回填空间狭窄、回填深度较大、回填土夯实质量不稳定等难题。传统工艺多采用素土或者灰土分层使用小型夯实设备进行施工,施工难度较大、回填工期较长、回填的质量还难以控制,综合本项目“工期紧、任务重”等要求,本项目肥槽回填采用固化土。

2 预拌固化土原材料

①土料。优先采用开挖弃土质量较好、数量大的黏土、粉土、砂土等,有机质含量不大于 5%,其颗粒最大粒径不大于 50mm。未经处理的污染土不得作为固化土的原材料。

②固化剂。土壤固化剂为以 CaO、活性 Al2O3和 SiO2为主要成分的无机水硬性胶凝材料,其技术原理为:复合矿物设计+化学激发作用。

固化剂抗压强度应使固化土的强度达到要求的强度值。……

登录APP查看全文

猜你喜欢
施工技术
建筑混凝土施工技术要点及有效对策分析
桥梁预应力工程的施工技术研究
高压输配电线路工程施工技术控制之我见
试析建筑工程施工技术及其现场施工管理探讨
浅析水利工程建设中的混凝土施工技术与施工管理
探讨水利水电工程防渗墙的施工技术
高层建筑主体结构施工技术及质量控制研究
施工技术在水利水电工程中的重要应用探究
水利水电工程建筑的施工技术及管理分析
试论关于水利工程冬季施工技术