【摘 要】为确保天津新一代运载火箭产业化基地(简称天津新区)顺利开展建设、管理和运营,提出综合计划精益化管理总体思路,包括:充分结合天津新区管理现状;充分运用PDCA循环法实现迭代升级;充分利用Project软件实现图形化和动态化跟踪控制。通过近五年精益化计划管理实践,综合计划管理取得显著成效,天津新区各项工作圆满完成。
【Abstract】In order to ensure the successful development, construction, management and operation of Tianjin New Generation Launch Vehicle Industrialization Base (Tianjin New Area), the paper puts forward the overall plan of lean management for integrated planning. Including: fully combining the management status of Tianjin New Area, fully using PDCA cycle method to realize iterative upgrading; make full use of project software to achieve graphical and dynamic tracking control. Through the lean plan management practice in the last five years, the comprehensive plan management has achieved remarkable results. All the work in Tianjin New Area has been successfully completed.
【关键词】综合计划;精益化管理; PDCA
【Keywords】integrated plan; lean management; PDCA
【中图分类号】TU27 【文献标志码】A 【文章编号】1673-1069(2018)03-0042-02
1 天津新区开展综合计划精益化管理的必要性
1.1天津新区概况
火箭院于2007年10月与天津经济技术开发区签订合作协议,在开发区建设新一代运载火箭产业化基地,此区域于2013年建设完成。
1.2 天津新区综合计划管理的特点
天津新区综合计划不同于一般的施工计划或生产计划,包含天津新区园区管理、项目建设及园区运营三个相对独立却内部统一的计划。综合计划是天津新区管理的中心环节,如何将“管理、建设、运营”有机结合,三方面工作形成一个整体,做到各方面工作能够相互促动、齐头并进、全部达标,是计划管理的关键。
2 精益化计划管理工具简介
2.1 PDCA循环法
PDCA循环法:分为计划(Plan)、实施(Do)、检查(Check)、处理(Action)四个阶段,对于没有解决的问题,应提交下一个PDCA循环去解决,它是由提高每一过程质量到提高总体质量的循环反复,是螺旋式上升迭代的过程。
2.2 Project软件
Project软件:Microsoft Project是一个常用的项目管理工具,不仅可以快速、准确地创建项目计划,而且可以帮助项目经理实现项目进度、成本的控制、分析和预测,使项目工期大大缩短,资源得到有效利用,提高经济效益。……