丁宁
摘要:结合丹大铁路草莓沟2号隧道下穿既有盘道岭公路隧道交叉段跨度大、间距小、岩石破碎等施工难点的工程实例,总结铁路隧道下穿施工采用超前洞身双层大管棚、三台阶法、控制爆破、双层钢架初期支护等工艺特点、施工工艺流程及控制要点,可为类似工程的施工提供参考。
Abstract: According to the engineering example of the No.2 tunnel of Dandong-Dalian Railway passing through the existing section of Pandaoling highway tunnel with large span, small distance and broken rock, the technical features, construction process and control points of advance hole double pipe shed, three steps method, controlled blasting, double-shelves initial support are summarized, which can provide reference for the construction of similar projects.
关键词:铁路隧道下穿;跨度大;间距小;施工技术
Key words: railway tunnel underpassing;large span;small distance;construction technology
中图分类号:U455 文献标识码:A 文章编号:1006-4311(2018)11-0152-04
0 引言
草莓沟2#隧道进口位于草莓沟村东,出口位于山城一组南侧,全长4262m,为单洞双线隧道,场区地处丘陵,隧道内埋深约20~150m。隧道于2010年10月份开工,至2015年7月份竣工。隧道于TJLDK158+141-TJLDK158+181里程范围下穿既有盘道岭公路隧道,交叉影响跨度40m,结构净距为7.47m,下穿处围岩等级为Ⅴ级。为实现下穿段隧道施工安全及既有公路隧道内的行车安全,隧道下穿段施工采用超前洞身双层大管棚,并辅以双层钢架等超强支护措施,实现安全穿越。
1 施工工艺及工序
1.1 工艺特点
针对丹大铁路草莓沟2号隧道下穿既有盘道岭公路隧道交叉段存在跨度大、间距小、岩石破碎以及危及既有公路隧道形成安全等特点。开挖前采用超前双层大管棚进行预支护与岩体形成双层载拱,有效控制岩体下沉、变形、掌子面位移,对交叉隧道起到显著的防护作用。开挖采用三台阶法,既能保证开挖时的安全稳定,又能保证交叉段尽早形成初支及二衬衬砌封闭的稳定状态。采用控制爆破对公路隧道结构的最大振动速度控制在10cm/s以内。……