以某小学体育馆为工程背景,通过ANSYS建立有限元模型,考虑不同跳跃频率、跳跃人数和跳跃次数的荷载作用,对大跨度预应力混凝土次梁楼盖结构进行竖向振动模拟分析,并进行现场实测,结果表明:修正半正弦平方荷载模型模拟单人跳跃荷载所得分析结果与实测值相对误差为12.98%,比较接近;多人同步跳跃所导致的楼盖竖向振动加速度随人数的增加而增加,近似呈正比关系;考虑多人跳跃难以严格同步,引入倍增因子对跳跃荷载模型进行修正,与实测值验证较为接近。

关键词:跳跃荷载;楼盖;振动;模拟分析

中图分类号:TU378.2

文献标志码:A文章编号:16744764(2018)03006105

Abstract:

A stadium of primary school was taken as an example, by establishing the finite element model with ANSYS, the vertical vibration of longspan prestressed secondary beams floor system worked with different jumping frequency, number of persons and jumping numbers were analyzed. The results show that, compared with the measured values, the modified halfsincepower model has a relative error of 1298%, which is closed to the measured values; vertical vibration acceleration caused by different people jumping synchronously increases with number of persons rising; considering the people cant jump synchronously the multiplication factor is introduced to correct the jumping loads model.

Keywords:

jumping loads; floor; vibration;simulation analysis

为了解决人致荷载所导致的竖向振动问题,可以设置减震器[1]和阻尼器[2]等,但这会增加建筑成本,并且由于人群活动的短时随机性,这并不是解决楼盖振动的最佳方法。从结构本身着手优化,在梁下增设底板,既可以增加楼盖刚度、减小振动,又可以节省吊顶,是合适的方案。对于楼盖结构,有节奏跳跃极有可能是其最不利的运动形式[37]。鉴于尚无相关的研究成果,笔者依据实际建造的工程,对带底板的大跨度预应力次梁楼盖在跳跃工况下的振动响应进行分析,并结合实测结果评价模拟分析的准确性。

1工程概况

研究背景为重庆市铜梁区某小学体育馆,该结构为地上3层的混凝土框架结构,每层中部各有一夹层。2层楼盖采用大跨度预应力混凝土次梁楼盖(如图1)。……

登录APP查看全文

猜你喜欢
振动
振动的思考
科学大众(2023年17期)2023-10-26 07:39:14
某调相机振动异常诊断分析与处理
大电机技术(2022年5期)2022-11-17 08:12:48
振动与频率
天天爱科学(2020年6期)2020-09-10 07:22:44
This “Singing Highway”plays music
具非线性中立项的广义Emden-Fowler微分方程的振动性
中立型Emden-Fowler微分方程的振动性
基于ANSYS的高速艇艉轴架轴系振动响应分析
船海工程(2015年4期)2016-01-05 15:53:26
主回路泵致声振动分析
UF6振动激发态分子的振动-振动驰豫
计算物理(2014年2期)2014-03-11 17:01:44
基于扭摆振动的转动惯量识别方法