吴卉芬


摘 要:对大型地下厂房开挖技术、开挖方法及高边墙变形检测技术进行研究,对提升工程建设质量与施工技术管理效率具有重要意义。本文以某工程作为研究对象,对该项目地下厂房顶拱层开挖技术问题进行研究,分析该厂房顶拱的受力特征,并运用“新奥法”概念针对厂房顶拱层不同围岩状况下开挖施工程序进行合理选择,最终确定不同围岩地质条件下的开挖施工方法,具有重要的理论与实践意义。
关键词:水电站;地下厂房;顶拱;施工技术
中图分类号:TV554文献标识码:A文章编号:1003-5168(2018)31-0070-03
Analysis of Construction Technology for Top Arch Excavation of
Large Underground Powerhouse of Hydropower Station
WU Huifen
(SINOHYDRO Bureau 12 Co., Ltd,Hangzhou Zhejiang 310000)
Abstract: Research on large underground powerhouse excavation technology, excavation method and high side wall deformation detection technology is of great significance to improve the construction quality and construction technology management efficiency. This paper took a project as the research object, studies the excavation technology of the top arch of the underground powerhouse of the project, analyzed the stress characteristics of the top arch of the plant, and uses the concept of “new Austrian law” to target different surrounding rock conditions of the top arch of the plant and finally determined the excavation construction method under different surrounding rock geological conditions, which had important theoretical and practical significance.
Keywords: hydroelectric power station;underground plant;top arch;construction technology
1 当前大型地下厂房施工状况分析
我国对于隧洞开挖方法的研究起步相对较晚,但研究速度较快。自20世纪60年代以来,在隧洞开挖实践中,我国就开始推广应用喷锚支护新技术[1]。根据相关统计,至1981年底,我国应用喷锚支护技术的地下工程和井巷,其长度累计已达7 500km[2]。鲁布革水电站引水隧洞于20世纪80年代开始动工,在施工过程中,应用了成套的地下工程开挖支护设备,凿岩台车、全断面光面爆破和非电毫秒雷管等技术也在工程中得到使用,平均月进尺达231m,甚至打破了月进尺373.5m的最高纪录[3]。此外,二滩水电站、小浪底水电站、广州抽水蓄能电站也都采用了钻孔、装载运输设备等现代化技术,使得我国地下工程施工效率与质量得到大幅提升。
广蓄一期工程地下厂房施工项目,在施工中遵循了“平面多工序、立体多层次”的施工原则,取得了良好的施工效果。……