郑静

摘要:随着我国电力系统体质改革的深入,输变电工程成为电网建设的重要环节,直接关系着电网的稳定运行,因此,对输变电项目采取项目后评价尤为重要,通过对输变电项目全过程的评价,找出项目建设中存在的不足及客观规律,加以改善,解决施工过程中规划不科学、投资成本高,建设工期长等问题,从而为后续的输变电项目提供科学、可靠的参考依据。因此,本文结合输变电工程的特变,对输变电项目后评价的内容及方法进行探究。
Abstract: With the deepening of the physical system reform in China's power system, power transmission and transformation projects have become an important part of power grid construction and is directly related to the stable operation of the power grid. Therefore, it is especially important to adopt post-project evaluation for power transmission and transformation projects. It is necessary to evaluate the whole process of the project, identify the deficiencies and objective laws in the project construction, improve them, and solve the problems of unscientific planning, high investment cost and long construction period in the construction process, so as to provide scientific and reliable reference for the subsequent power transmission and transformation projects. Therefore, this paper, combining the special changes of power transmission and transformation projects, explores the content and methods of post-evaluation of power transmission and transformation projects.
關键词:输变电;项目后评价;模糊层次分析法
Key words: power transmission and transformation;post-project evaluation;fuzzy analytic hierarchy process
中图分类号:TM72 文献标识码:A 文章编号:1006-4311(2018)29-0010-02
1.1 项目后评价的概念
项目后评价是项目生命周期中不可缺少的重要环节,是对项目全过程的评价。针对已完工项目投产运行一段时间后,对项目的目标实现、实施过程、经济、影响及可持续性方面进行系统综合分析及全面的客观评价。通过评价的结果,寻找存在的不足及缺陷,总结项目中的经验教训,并加以改进实施,制定科学合理的建设计划,为后续项目提供科学的参考依据。
1.2 项目后评价的特点
项目后评价是依据实际情况,采取客观、科学系统的方面进行全面的评价,主要具备以下四个特点:
1.2.1 真实性
项目后评价是以实际情况为基础,对已完工的项目的设计实施、验收竣工,以及运行情况进行科学、系统的分析,分析的数据来源真实,且均为项目投产运行一段时间的有效数据,项目后评价具有真实性。……