大秦线延庆至下庄牵引供电系统临时改造方案

2018-09-20 03:16:32张亚宾杨建兴辛荣亮
价值工程 2018年29期

张亚宾 杨建兴 辛荣亮

摘要:大秦线一期工程韩家岭~大石庄段于1988年12月28日开通运营,牵引供电系统按年运量1亿吨设计,大秦线2002年完成货运量10231万吨,已超过原设计的输送能力,牵引供电能力极为紧张,尤以延庆~下庄段为甚,已严重影响机车正常运行。本文介绍了延庆~下庄段应急改造工程牵引供电系统设计的四个“第一”,确保了大秦线2004年年运量1.5亿吨、2005年年运量2亿吨目标的实现,供重载铁路牵引供电系统设计参考。

Abstract: Hanjialing to Dashizhuang line, which is the first project of Datong-Qinhuangdao line, was opened and operated on December 28, 1988. The traction feeding system of Datong-Qinhuangdao line was designed on the base of 100 million tons per year volume, but the volume reached to 102.31 million tons in 2002, which was much more than original design transportation capacity. Over loading made traction power feeding system extremely tight, especially in Yanqing to Xiazhuang line, and this had seriously affected the normal operation of locomotives. This paper introduces four "NO.1" in the design of the traction power feeding system in emergency reconstruction project of Yanqing to Xiazhuang line, which can ensure to achieve the goal of year volume reaches up to 150 million tons in 2002 and 200 million tons in 2004. This paper can also be considered as the reference of the traction power feeding system design.

關键词:延庆至下庄;应急工程;牵引供电系统;改造方案

Key words: Yanqing to Xiazhuang;emergency project;traction feeding system;reconstruction plan

中图分类号:TM922.3 文献标识码:A 文章编号:1006-4311(2018)29-0140-03

0 引言

大秦线是我国第一条双线电气化、开行重载单元式列车的运煤干线,西起大同市,东至港口城市秦皇岛,主要承担晋北、蒙西及西北部的煤炭外运任务。大秦线开通14年来,运量逐年增长,2002年完成货运量10231万吨,已超过原设计10000万吨的输送能力,根据运量预测,2004年大秦线的煤炭运输量为1.5亿吨,2005年煤炭运输量将达到2亿吨以上。因此,大秦线牵引供电能力普遍不适应运输组织的需要,特别是延庆~下庄供电臂接触网的供电能力成为限制大秦线运量进一步提高的瓶颈。为了缓和大秦线延庆~下庄段的供电能力紧张,以及为增加重载列车、减少车流密度、预留天窗时间为下阶段的2亿吨扩能改造施工创造条件,有必要对延庆~下庄段实施应急改造,对供电设备能力进行加强,以满足2004年大秦线年运量1.5亿吨目标的实现。

1 既有牵引供电系统概况

1.1 牵……