吴欣
摘 要:对于需在施工期间保持通行的高速公路扩建工程,施工期间交通组织是工程的关键,而路面施工阶段又是重中之重,本文章结合南京机场高速公路扩建工程实践,分析总结高速公路扩建工程路面施工期间交通组织思路与步骤,以期为高速公路改扩建工程交通组织方案提供参考。
关键词:高速公路;改扩建路面施工;交通组织
中图分类号:U412.1 文献标志码:A 文章编号:2095-2945(2018)25-0085-02
Abstract: Traffic organization is the key of the highway extension project which needs to be kept in traffic during the construction period, and the road surface construction stage is the most important one. This paper, in view of the practice of Nanjing Airport expressway expansion project, analyzes and summarizes the ideas and steps of traffic organization during pavement construction of expressway extension, project in order to provide reference for traffic organization scheme of expressway reconstruction and extension project.
Keywords: highway; reconstruction and extension of pavement construction; traffic organization
高速公路改扩建施工对原高速公路交通影响较大,而路面施工又是对交通影响最大的阶段,如何保证路面施工阶段的道路通行能力,是整个交通组织的关键。本文以南京机场高速公路扩建工程路面施工为例,对改扩建路面施工交通组织进行探讨。
1 工程概况
南京机场高速公路翠屏山互通至机场段,路线长23.76
2Km。原建设采用双向四车道高速公路标准,路基宽度26m,设计速度120Km/h。
现状沿线共设置5处互通式立交,分别为花神庙互通、翠屏山互通、南庄枢纽、禄口互通和机场枢纽,在机场枢纽北设置主线收费站1处,在翠屏山互通设置服务区1处。
本次扩建工程采用沿老路两侧直接拼接的拓宽方式,主线扩建为双向八车道高速公路,路基宽度42.0m。
翠屏山互通、南庄枢纽、禄口互通及机场枢纽4处互通式立交需要进行改造,与扩建后的主线顺接;在正方大道位置新增秣陵互通(设置管理分中心及养排中心)1处,主线站扩建为13进13出(含每侧各1条贵宾车道)。
2 交通组织工程阶段
本项目路面结构层施工期间涉及交通组织的主要工程项目有[1]:……p>