火力发电厂调试过程中热控的常见问题研究

2020-05-21 10:01:31马凯凯
科技创新与应用 2020年15期
关键词:火力发电厂调试

马凯凯

摘  要:火电厂热控系统装置相对较为复杂,而热控调试作为主机以及附属设备安装、设计、制造检验重要手段,会对电厂运行安全性、稳定性产生直接影响。文章将重点对火力发电厂调试过程中常见的热控问题展开分析,并会以问题为引导展开应对策略研究,会针对热控系统运行优化提出几点建议,旨在提升热控系统运行质量,保证火力发电厂生产水平。

关键词:检测设备;热控系统;调试;火力发电厂;逻辑组态

中图分类号:TM621        文献标志码:A 文章编号:2095-2945(2020)15-0123-02

Abstract: The thermal control system of thermal power plant is relatively complex, and thermal control debugging, as an important means of installation, design, manufacturing and inspection of mainframe and ancillary equipment, will have a direct impact on the safety and stability of power plant operation. This paper will focus on the analysis of the common thermal control problems in the debugging process of thermal power plants, take the problems as the guidance to carry out response strategy research, and will put forward some suggestions for the operation optimization of thermal control systems, in order to improve the operation quality of thermal control systems and ensure the production level of thermal power plants.

Keywords: testing equipment; thermal control system; debugging; thermal power plant; logic configuration

热控保护系统是火电厂安全运行关键要素,做好热控保护,会对电力稳定、安全生产产生积极影响,是火电厂关注重点内容。就目前热控系统运行情况来看,部分发电厂在实施调试过程中,可能会因為设备检测不到位以及操作不规范等问题影响,而导致热控系统没有达到预期运行要求,致使电力生产受到直接影响。鉴于此,做好常见热控问题分析,科学展开热控问题优化处理,极为必要。

1 火力发电厂调试过程中的热控问题

1.1 设备检测不到位

按照规定要求,在实施调试之前,需要对系统各项设备展开全面性检测,确定电缆连接以及冗余措施等是否达到标准之后,才可逐步展开调试。而部分单位并没有认识到设备检测的重要性,设备检测存在形式化以及检测不全面等状况,很容易会使设备受到损伤[1]。同时没有事前制定紧急应对预案,也会对紧急事故处理产生严重干扰,可能会出现设备受损坏较为严重的状况,会造成不必要的安全事故以及经济损失。……

登录APP查看全文

猜你喜欢
火力发电厂调试
基于航拍无人机的设计与调试
电子制作(2018年12期)2018-08-01 00:47:44
我国第一座超百万千瓦火力发电厂建成
兰台世界(2017年11期)2017-06-22 14:17:18
核电厂主给水系统调试
中国核电(2017年1期)2017-05-17 06:10:11
无线通信中频线路窄带临界调试法及其应用
电子制作(2017年19期)2017-02-02 07:08:38
大型火力发电厂烟气脱硫控制网络结构渐变趋势
调压柜的调试与试运行探讨
工业电气设备控制系统的安装与调试
火力发电厂输煤系统煤尘综合治理探讨
浅谈如何做好海外火力发电厂总承包工程
音频处理器的调试