摘 要 本文以江西省某矿山竖井钢井架安装工程为例。重点介绍了竖井钢井架施工的主要施工内容,以及在施工过程中应注意的各项保证施工质量的方法和保障施工安全的管理措施,为类似的矿山竖井工程施工提供了参考和借鉴。
关键词 竖井施工;施工质量;安全管理;参考
Abstract In this paper, the installation of a new vertical well steel derrick in the development and utilization of the tantalum tantalum tantalum ore body in Dajishan, Jiangxi Province, is an example. This paper focuses on the main construction contents of the construction of the shaft steel derrick, as well as the methods to ensure the quality of construction and the management measures to ensure the safety of the construction, which provide reference and reference for the construction of similar mine shaft silos.
Key words Shaft construction; Construction quality; Security Management; References
钢井架是矿山竖井在地面的主要建筑物,是竖井与外接进行联系的主要通道,对于整个竖井的结构起着“咽喉”的作用。相比于其他材料所构成的井架、井塔,钢井架具有强度高、抗震好、造价低以及施工建设周期短等显著特点,因而被国内外的矿山所广泛使用[1]。
1工程概况
1.1 概况
该竖井的立井井筒直径为5.5m,井口标高为+593.5m,井底标高为+242.7m,新竖井提升采用罐笼配平衡锤提升,罐笼及平衡锤均为方钢罐道导向。井筒内设梯子间、管子间、电缆间。井筒有5个中段设马头门,其中467m为单面马头门,417m、367m、317m、267m为双面马头门。
新竖井井架为四斜柱式钢井架,主要构件采用箱形截面。该井架设置二层永久提升天轮平台,井架四斜柱与混凝土基础地脚螺栓连接,井架高32.2m;套架为H型钢框式钢结构,立柱腿与混凝土基础用地脚螺栓联结固定;主、副斜腿为斜双柱箱型钢结构,斜腿柱脚与混凝土基础用地脚螺栓连接;套架与斜腿通过拉结梁连接。井架上天轮中心标高+26.725m,下天轮中心标高+20.725m。
1.2 特点
①井架主斜腿部分总重量达到116.64吨,构件吊装重量较重;外形尺寸大;井架斜腿最高为32.2m,吊装高度较高。吊装采用多台汽车吊抬吊法[2],故吊装设备多、吨位大。……