保山城市地下综合管廊顶管施工技术研究

2020-08-03 02:02:35代绍海尹川段军杨建雄
价值工程 2020年17期

代绍海 尹川 段军 杨建雄

摘要:城市地下综合管理具有多种施工方法,其中顶管施工法在一定的条件下也具有优越的技术经济性能。本文以保山象山路综合管廊的顶进施工为例,对顶管施工的关键施工环节包括沉井施工、下穿河道围堰压重施工、顶管施工等进行了详细的介绍,对施工技术的关键环节进行了分析,可为今后类似工程提供参考。

Abstract: There are many construction methods for urban underground comprehensive management, among which pipe jacking construction method has superior technical and economic performance under certain conditions. Taking the jacking construction of the comprehensive pipe gallery of Xiangshan Road in Baoshan as an example, this paper introduces the key construction links of the jacking construction in detail, including the construction of open caisson, the construction of cofferdam under the river, and the jacking construction, and analyzes the key links of the construction technology, which can provide reference for similar projects in the future.

關键词:综合管廊;沉井;顶管;下穿河道;纠偏

Key words: comprehensive pipe gallery;sinking well;pipe jacking;underpass river channel;correction

中图分类号:TU990.3                                     文献标识码:A                                  文章编号:1006-4311(2020)17-0161-02

1  工程概况

1.1 工程背景

保山象山路综合管廊工程位于云南省保山市隆阳区象山路,路线全长约5800m。本工程将在待建象山路下方敷设单舱综合管廊,断面尺寸B×H=2.4m×2.4m。将电力、通信、给水等管线纳入综合管沟。其中圆形顶管施工段位于保山市隆阳区青华海旁,顶管总长度为354m,为直线顶管。管道设计为钢筋混凝土F型管,内径?准3000mm,外径?准3800mm,管道坡度为0.366%。预制管节为单节2.5m,本段约采用单节管节约142节。该段采用不开槽开挖泥水平衡施工机械顶管施工,顶进推力约需1860t,顶管段平均埋深为7m,其中下穿东河段埋深为2.9m,施工时需采压重封水处理。管廊自西向东分别下穿青华路、青华湖公园、东河,分别由东西两侧工作井采用泥水平衡机械顶管施工向接收井顶进。

1.2 工程地质条件

本段管廊施工范围内的土层分布依次包括杂填土、黏土、含有机质黏土、黏土、粉土等,各层土体的分布及主要物理力学性质指标见表1所示。该段顶管施工需要下穿东河,东河宽度30m,河底淤泥厚度为400mm,水深600mm,河底到顶管管顶距离为2.9m。……