刘晓瑞

摘 要:引汉济渭水利工程岭北段TBM掘进通过断层破碎带时,受流渣状变质千枚岩、糜棱岩及夹杂断层泥砾影响,刀盘和护盾段被坍塌碎屑体卡死受困。为实现TBM脱困,在掘进面右侧围岩较好段,通过设置爬坡孔并采用风镐人工开挖纵向超前导洞,导洞迂回通过塌腔并开挖至刀盘前12 m后横向扩挖形成管棚工作室。在工作室反向大管棚支护条件下,开挖至受困刀盘处并实现TBM顺利脱困。小导洞迂回反向支护技术在TBM卡机脱困中的应用表明:①为防止坍塌体进一步碎胀挤压盾体,TBM脱困处理前需采用套拱完成盾尾急剧收敛段加固;②爬坡孔和纵向导洞需设置在围岩较好段,采用Φ32自进式锚管结合H150门型钢架支护,循环进尺控制在0.5 m以内;③按照“分区分段、由上及下、管前严注、短挖强支”原则,由纵向超前导洞向盾体两侧开挖横向小导洞处理坍塌体并设内外两层环形钢拱架,在拱架间灌注C30混凝土形成型钢混凝土结构,以此保护盾体并释压脱困。

关键词:TBM卡机;脱困;导洞迂回;反向支护;引汉济渭;秦岭隧洞

中图分类号:TV53 文献标志码:A

doi:10.3969/j.issn.1000-1379.2020.02.023

Abstract:Affected by phyllite, mylonite and fault gouge, cutter head and shield are frequently trapped by the collapsed debris in Qinling water delivery tunnel from Han to Weihe River. In order to achieve TBM relief,the climbing hole and the longitudinal leading guide hole were manually excavated with a pick through the better surrounding rock on the right side of the heading face. Then the guide hole, after passing through the collapse cavity and excavated to 12 m in front of the cutter plate, was excavated horizontally to form the pipe shed studio. Furthermore, under the supporting conditions of the large inverted pipe shed in the studio, the TBM was successfully extricated. The application of reverse large pipe-shed technology indicates that: a)in order to prevent the collapse body from further crushing and squeezing the shield, it is necessary to reinforce the sharp convergence section of the tail of the shield; b)Climbing hole and longitudinal guide hole should be set in the better section of surrounding rock with 32 self-feeding anchor pipe and H150 steel frame and the stepping distance is controlled within 0.5 m; c)In accordance with the conception“partition and segmentation, from up to down, pipe in advance and strictly grouting, short excavation and strong support”,the collapse body is treated by excavating the transverse small guide hole from the longitudinal leading guide hole to both sides of the shield body and the inner and outer ring steel arches with C30 concrete poured between the arches are used to protect the shield body and relieve pressure.

Key words: TBM jamming; out of trouble; indirect guide hole; reverse supporting;Hanjiang-to-Weihe River Valley Water Diversion Project; Qinling tunnel

我國水资源空间分布不平衡,为合理利用水资源、实现水资源合理调配,跨流域调水、引水隧洞工程不断涌现。TBM因安全、高效、环保、机电一体化程度高的优点而被广泛应用于长大引水隧洞掘进施工。然而,在穿越断层破碎带、软岩大变形、高地应力等特殊地质段落时,TBM时常因围岩碎胀挤压而出现卡机事故,必须进行脱困处理。……