曾联金



摘 要:在山区修建公路时,经常会遇到深挖路堑,在这种情况下,往往采用预应力锚索格子梁植草防护的形式对路堑高边坡进行防护。保证施工质量及安全,是此类工程的重中之重。本文以某高速公路项目为背景,对路堑多级高边坡阶梯分层加固施工关键技术进行探讨。
关键词:路堑高边坡;预应力锚索;格子梁;动态监控
中图分类号:U418.52文献标识码:A文章编号:1003-5168(2021)15-0104-04
Abstract: When building highways in mountainous areas, deep cuts are often encountered. In this case, pre-stressed anchor cables and lattice beams are often used to protect the high side slopes of the cuts. Ensuring construction quality and safety is the top priority of this type of project. This paper took a highway project as the background, and discussed the key technology of multi-level high side slope step-by-step reinforcement construction.
Keywords: high cutting slope;prestressed anchor cable;lattice beam;dynamic monitoring
预应力锚索格子梁植草防护作为一种路基边坡防护形式,被越来越多地应用到各等级公路中,尤其是在高速公路中的应用最为广泛。该防护形式具有支护高度不受限制、造价低、自重轻、稳定性好等优点,在路堑高边坡支护中发挥着重要作用。此工艺通过格子梁承受来自锚索的预应力,然后再传递至被锚固的路堑边坡土层中,从而改变路堑边坡土体受力状态,以达到稳固路堑边坡的目的[1]。
1 工艺流程
预应力锚索格子梁植草防护的工艺流程为:施工准备→搭设脚手架平台→钻机就位→钻进成孔、清孔→锚索安装→砂浆准备→注浆→锚索养护及格子梁施工→混凝土养护→锚索张拉、锁定→锚头封闭。具体施工流程如图1。
2 预应力锚索技术操作要点
2.1 作业平台搭设及受力验算
2.1.1 作业平台搭设。作业平台采用Φ48 mm×3.5 mm的Q235钢管搭设,三向间距均为1.5 m。最下缘钢管固定于坡脚边沟沟底,其余立杆均沿坡面固定于边坡土层或岩体内,斜杆使用3层钢管搭设。最下缘的部分作为斜撑,并固定于坚实的地面上。……