摘    要:本文简要介绍了JB118海上平台冲桩系统调试过程中,当平台降船处于水上浮态时,冲桩系统从海底门取水时出现冲桩泵进口真空度大、冲桩泵运行异常振动的现象。为此,对该问题进行分析并提出解决方案,最终调试成功并通过验收。

关键词:冲桩系统;冲桩泵;调试;真空度;振动

中图分类号:U664.5                                  文献标识码:A

Commissioning and Analysis of JB118 Jetting Pump for

Windmill Installation Platform

YANG Wei

( China Merchants Heavy Industry (Shenzhen) Co., Ltd., Shenzhen 510725 )

Abstract: This paper introduces the problems of large vacuum degree at the inlet of the jetting pump and abnormal vibration in the operation of the jetting pump occurred when the offshore windmill installation platform is in floating state and jetting piping system draws water from sea chest during the commissioning of the jetting piping system of JB118 platform, and then analyzes the problems and proposes the solutions. Finally, the commissioning is successful and accepted.

Key words: Jetting piping system; Jetting pump; Commissioning; Vacuum degree; Vibration

1     前言

CMHI-116 JB118海上风车安装平台原入ABS船级社、挂巴哈马群岛船旗,后转入CCS船级社、挂中国旗。本平台为矩形船体,4根桩腿,配备MSC液压升降系统的自升式平台:主吊机1 000 t,主要用于北海南部45 m水深范围内的风电设备安装等海洋工程建设;本平台船体总长75.9 m、 型宽40.0 m、 型深6.0 m、 设计吃水4.2 m; 四根圆柱形桩腿,长度81.55 m、 直径3.5 m;桩靴长度7 m、宽度6.8 m、高度2.28 m。

原平台未配置冲桩系统,改造增加冲桩系统。海上风电安装平台,主要由上部平台结构、升降装置、桩腿、桩靴等组成。平台的自重和载荷是通过桩腿和桩靴插入海底来承受,以保证平台工作时的稳性和安全;当某区域作业完成后,需要拔起桩腿将平台转移到下一个工作区域。由于桩靴表面积大,且海泥易吸附在桩靴表面,拔桩的阻力大。为此,风电安装平台往往配备一套冲桩系统,以高压海水冲刷掉桩靴上的泥土,破坏海泥土层对桩靴的吸附力,减小拔桩阻力,使拔桩顺利进行。

2    冲桩系统设计

增加的冲桩系统,包括:2台冲桩泵(1用1备),為桩靴冲桩系统提供高压海水进行冲桩;冲桩系统设计选用泵的参数为:流量40 m3/h,压力为6 Mpa,管路通径选型随之匹配。……

登录APP查看全文

猜你喜欢
调试振动
振动的思考
科学大众(2023年17期)2023-10-26 07:39:14
喷水推进高速艇尾部振动响应分析
This “Singing Highway”plays music
基于航拍无人机的设计与调试
电子制作(2018年12期)2018-08-01 00:47:44
振动搅拌 震动创新
中国公路(2017年18期)2018-01-23 03:00:38
中立型Emden-Fowler微分方程的振动性
核电厂主给水系统调试
中国核电(2017年1期)2017-05-17 06:10:11
无线通信中频线路窄带临界调试法及其应用
电子制作(2017年19期)2017-02-02 07:08:38
调压柜的调试与试运行探讨
工业电气设备控制系统的安装与调试