张爱书
摘要:针对近些年来,高架施工过程中出现质量与安全问题,结合我公司在虹桥机场监理所采取的各项措施,严格贯彻公司“精细化、过程化监控”控制思路,做了一次探索,如:混凝土箱梁施工质量控制“十项”要点与钢、叠合箱梁现场焊接“七项”要点。实际监理中也取得了一些显著成绩:获得上海市政金奖、优秀集团、个人记功等,值得作为经验推广。
关 键 词:混凝土箱梁 钢 叠合箱梁 精细化 过程化监控质量控制
中图分类号: U448 文献标识码:A 文章编号:
Abstract:In recent years, elevated appear in the process of construction quality and safety problems, combined with our company in the Hongqiao airport management measures adopted, strict implementation of the company" refinement, process monitoring" to control train of thought, made a probe, such as: concrete box beams in the construction quality control of" ten" points and steel, laminated combined box beam welding points of" seven". The actual supervision has made some remarkable achievements: Shanghai municipal award, outstanding group, individual merits, is worth as experience to promote.
Key Words: Concrete box girder; Steel; composite box beam; Fine chemical; Process monitoring and quality control
1项目概况
桥综合交通枢纽工程内快速集散系统工程监理3标工程范围:南至七莘路,SN6、SN5路,西至SN4路、XH2路以及EW4,东至机场航站用地边线,北至航站楼,共有41条匝道组成,总里程有10公里,其中φ600PHC管桩3058根、承台385只、桥台10个、立柱386根、盖梁有3个、箱梁共有124联 (35联为普通钢筋混凝土连续箱梁,钢连续箱梁5联,叠合梁11联,其余73联为预应力混凝土箱梁)。
2项目监控存在难点
项目总体施工建设形成以桥梁工程施工为关键线路,道路及下水道工程交叉施工模式。
合同工期较短,施 “人、机、料、资金”投入强度大,匝道施工曲线较多,同时又立体交叉施工,相关市政配套单位陆续进场,干扰大;
施工现场作业队伍多、业务素质相关较大,专业队伍相对较少;
施工原材料采购困难,批次多,抽查难度大;
施工作业面多,人员投入较大,监控难度。
3项目监控主要思路与方法
结合公司贯标思路:依照公司的“每道工序,严格监控;每个工程,精益求精;遵纪守法,不断满足和超越顾客的要求和期望”的质量方针和科学管理”,提出:“精细化、过程化”监控,建设一流世博工程,提高监理服务整体质量,强化监理社会与职业责任的思路。……