赵宏志
摘 要:本项目隶属于煤矿开采领域,许疃煤矿通过提前对综采工作面安装及后期回采的各项要求进行仔细研究,超前谋划,在掘进期间完成综采工作面安装回采的各项准备工作,实现采掘无缝对接。杜绝了以前掘进期间只满足自身的使用,造成安装前需要进行大量整改工作的情况,有效解决了采掘之间的衔接问题,节约大量时间和人力物力,对采掘提效工作产生了极为明显的推进作用。
关键词:综采工作面;一站到位;应用
中图分类号:TD79 文献标志码:A 文章编号:2095-2945(2018)18-0159-02
Abstract: This project belongs to the field of coal mining. Xutuan Coal Mine carefully studies the installation of fully mechanized coal face and the requirements of later mining in advance and planning ahead of time, completes all the preparatory work of installation and mining of fully mechanized mining face during the excavation period, and realizes the seamless docking of mining. It has put an end to the fact that the previous excavation period only satisfied its own use, resulting in a large amount of rectification work needed before installation, effectively solved the problem of convergence between mining and excavation, and saved a great deal of time, manpower and material resources. It has a very obvious promoting effect on the mining efficiency work of mining.
Keywords: fully mechanized mining face; one stop in place; application
1 概况
许疃煤矿是属于淮北矿业集团有限责任公司下属的一座现代化大型生产矿井,位于蒙城县许疃镇境内,是国家九五重点建设项目,1997年10月20日破土动工,2004年7月8日实现联合试运转,11月8日正式投产。许疃煤矿连续多年荣获全国煤炭行业安全高效矿井称号,并被评为全国文明煤矿。
现代化煤炭矿井机械化程度逐年增高,综采工作面安装频率上升趋势十分明显,以往掘与装、装与采之间两个标准,灾害治理工程单打独斗,往往在掘进结束后,需要更换无极绳、整改轨道、单独设计组装硐室等,方具备综采工作面安装条件;安装后需要整改支架、运输机、破碎机等方可投入正常生产,而在掘、装、采过程中,瓦斯治理的顺层孔、高位孔等治理工程之后,直接影响回采。以上情况严重制约着采掘提效的效果。
许疃煤矿通过提前对综采工作面安装及后期回采的各项要求进行仔细研究,超前谋划,在掘进期间完成综采工作面安装回采的各项准备工作,真正意义上做到采掘无缝对接。……