摘要:为有效保证装配式桥梁施工质量,在实际工程施工过程中,针对其施工质量存在的问题进行因素分析,并采取相应的措施进行控制,能够有效地预防问题的发生,从而提高施工质量。本文以上海某城市高架桥工程为例,运用模糊层次综合评价法建立数学模型,借助MATLAB R2014a软件辅助计算,对装配式高架桥施工过程中的主要质量影响因素进行分析,得出该工程施工过程质量因素影响程度属于“极高”等级,并提出具有针对性的质量控制措施。

Abstract: In order to effectively ensure the construction quality of prefabricated bridges, in the actual construction process, the problems existing in the construction quality are analyzed and corresponding measures are taken, which can effectively prevent the occurrence of problems and improve the construction quality. This paper takes an urban viaduct project in Shanghai as an example, establishes a mathematical model by using the FAHP,  analyzes the main quality influencing factors during the construction of the prefabricated viaduct with the aid of MATLAB R2014a software, and finds that the degree of influence of the quality factors in the construction process of the project belongs to the "extremely high" level, and proposes targeted quality control measures.

关键词:模糊层次综合评价法(FAHP);装配式高架桥;施工质量控制

Key words: FAHP;prefabricated viaduct;construction quality control

中图分类号:U448.28                                   文献标识码:A                                  文章编号:1006-4311(2020)23-0109-03

0  引言

党的十九大报告提出绿色生态发展,“质量第一、效益优先”的发展要求,加快推进了装配式建筑在我国建设领域的发展。装配式结构具有节约成本、绿色环保、缩短工期等诸多优点,因此,广泛应用于城市高架桥的建设。随着科技进步,装配式施工技术得到了很大的提升,但是在施工过程中仍存在一定的质量问题,导致装配式高架桥质量受到极大的影响。2019年6月24日,河南省郑州市一在建高架桥墩北半幅发生落梁,预制梁在现场安装对接过程中零时支撑承载力不够导致桥梁失稳;2019年10月10日,江苏无锡312国道一座高架桥发生桥面侧翻事故,已致3人遇难,2人受伤。因此,为了预防装配式高架桥安全事故的发生,有效保证施工质量,对工程施工进行质量控制分析是很有必要的。

目前,国内对预制装配式建筑施工质量管理及控制措施的研究已较为成熟,但针对高架桥施工质量控制的研究较少。……