中图分类号:TU2
摘要:
随着国民经济的发展,电网改造的进程也在加快。在电网改造建设过程中,变电站的建设数量呈现不断上升的趋势。为了节省用地、减少建筑面积、控制工程造价和与城建规划相协调,许多变电站都设计为综合自动化无人值班的变电站,采用全户内或半户内布置方案。在此种情况下,消防系统的正常运行对于变电站的安全生产显得更为重要。本文着重介绍变电站的各种消防技术措施及其工作原理和相应的设计方法。
关键词:变电站消防系统、水喷雾灭火系统、气体灭火系统、火灾自动报警系统
Abstract:With the development of national economy, the power grids oftheprocess is also accelerating. In the process of construction of power grids, the number of substation construction is showing a growing trend. To save space, reduce the building area, and control project cost , many substations are designed for unattended substation integrated automation, full indoor or semi indoor layout. In such cases, the normal operation of the fire protection system for substation safety in production is more important. This paper introduces a variety of technical measures and its working principle and the corresponding design method.
Keywords: substation fire protection system, water spray extinguishing systems, gas fire extinguishing system, automatic fire alarm system
变电站消防系统的设计可分为:总平面布置及建筑防火、消防灭火设备系统、通风空调防排烟、消防电气、电缆敷设及防火阻燃等几部分内容,以下对各个系统的设计原则一一作简略介绍。
一、总平面布置及建筑防火
变电站总平面布置消防设计主要依据《建筑设计防火规范》GB50016及《火力发电厂与变电站设计防火规范》GB50229。
变电站内火灾危险性为丙类且建筑面积超过3000m3的生产建筑周围宜设置环形消防通道。主变压器场地、高压电抗器场地周围应设置环形消防通道,当设置环形消防车道有困难时,可沿长边设置尽端式消防车道,并应设置丁字形回车道或回车场。消防车道的宽度不应小于4m,转弯半径不宜小于9m,道路上架空障碍物净高不应小于4m,可以满足消防车通道、运行、检修、安装等要求。以确保消防通道畅通无阻,在每一建(构)筑物发生火灾时,消防车可直达出事地点。……