郗晶 张晶莹
【摘要】随着国内市场经济的发展,火电厂要提高自身在市场中的竞争力,降低发电成本,提高火电厂的盈利,合理的工程造价管理是必不可少的,分析和研究火电厂工程造价可以更加合理的进行工程造价管理。本文从火电厂工程造价组成出发,分析了火电厂工程造价管理和控制、工程造价存在的问题以及改进措施,通过本文的分析和讨论以期对火电厂工程造价管理能有一定的指导意义。
【关键词】火电厂;工程造价;投资;管理
Brief Analysis on Project Cost Management of Thermal Power Plant
Xi Jing,.Zhang Jing-ying
(China Energy Construction Group Shanxi Electric Power Construction Co., LtdTaiyuanShanxi030012)
【Abstract】With the development of the domestic market economy, thermal power plants to improve their competitiveness in the market, reduce power generation costs, improve the profitability of thermal power plants, reasonable project cost management is essential to analyze and study the thermal power plant project cost can be more Reasonable project cost management. Based on the composition of the project cost of the thermal power plant, this paper analyzes the problems in the cost management and control of the thermal power plant, the problems existing in the project cost and the improvement measures. Through the analysis and discussion of this paper, the author has some guiding significance for the project cost management of the thermal power plant.
【Key words】Thermal power plant;Project cost;Investment;Management
1.前言
火電厂利用煤、石油、天然气等化石燃料作为燃料经过锅炉的燃烧将化学能转化为蒸汽中的内能,然后推动汽轮机做功发电,做完功的蒸汽在凝汽器中冷凝,通过给水泵完成循环。火电厂工程造价的控制贯穿与火电厂建设的整个过程,工程造价的控制水平高低,直接影响着火力发电厂的生产运营和盈利情况,加强火电厂工程造价管理至关重要。
2. 火电厂工程造价组成
(1)与其它工程一样,火电厂工程造价从总体上也可以分为建筑项目总投资(固定资产投资、流动资产投资)、固定资产投资包括(设备及工器具购置费用、建筑安装工程费用、工程建设其他费用,预备费、建设期贷款利息,固定资产投资方向调节税)、设备及工器具购置费用(设备购置费,工器具及生产家具购置费用)、设备购置费(设备原价和设备运杂费)、建筑安装工程费用(直接费、间接费、利润、税金)、建筑建设其他费用(土地使用费、与项目建设有关的其他费用、与未来企业生产经营有关的其他费用)以及预备费(基本预备费 涨价预备费)等几个部分,关于这几个部分投资及成本的讨论和计算方法可以参考文献的相关内容。……