摘 要:建筑施工现场各专业交叉作业复杂,人员较多,主体结构施工时在楼板上预留的线管,在填充墙施工前被破坏的情况时常发生。而且在填充墙施工时,往往将线管处三皮底砖预留孔洞,由线管处向两边砌筑,再进行二次配管开槽技术。该技术造成线管处底砖孔洞,孔洞填塞不密实,后期粉刷后造成空鼓。尤其在外墙部分,孔洞的防渗漏修补工作更是难点,造成施工成本增加。本文通过对填充墙底砖的现场预制加工,主体施工阶段开始砌筑预制底砖作为线管的成品保护措施,填充墙施工时直接作为底砖向两边开始砌筑施工,二次配管开槽时线槽开至预制底砖上部的技术探讨,达到了满足各项技术指标的要求,并且具有保证质量、施工方便、降本增效的特点。
关键词:主体预留线管保护;二次配管底砖免开槽;底砖预制块
Abstract: The cross operation of various disciplines on the construction site is complex and there are many personnel. The line pipes reserved on the floor during the construction of the main structure are often damaged before the construction of the infilled wall. Moreover, during the construction of infilled wall, the three bottom bricks at the line pipe are often reserved for holes, which are built from the line pipe to both sides, and then the secondary piping slotting technology is carried out. This technology causes the bottom brick hole at the line pipe, the hole filling is not dense, and the hollowing is caused after painting in the later stage. Especially in the exterior wall, the anti leakage repair of holes is more difficult, resulting in an increase in construction cost. In this paper, through the on-site prefabrication and processing of the bottom brick of the infilled wall, the prefabricated bottom brick is built in the main construction stage as the finished product protection measure of the line pipe, the masonry construction is directly started on both sides as the bottom brick during the infilled wall construction, and the technical discussion on the opening of the line slot to the upper part of the prefabricated bottom brick when the secondary piping is slotted, so as to meet the requirements of various technical indexes. It has the characteristics of ensuring quality, convenient construction, reducing cost and increasing efficiency.
Keywords: Main reserved conduit protection; Non slotting construction technology for bottom brick of secondary piping; Bottom brick precast block
一、工藝原理
以废旧模板为原材料制作预制块模具,预制块尺寸以三皮底砖为基数,预制块为中间开孔的阶梯状,模具可制作成多个预制块联排的形式。主体结构施工预留线管后,将预制块套在线管处,保护线管免遭破坏。后期填充墙施工时,此预制块作为底砖用,其余底砖向两边开始砌筑。二次配管开槽时,线槽开至预制块上部即可。
二、施工工艺流程
施工准备→模具制作→预制块制作→预制块安装→底砖砌筑→填充墙砌筑→开槽、安装线管→槽口修补→检查验收。……